The process from the event log
Map how claims really flow from the claims system's event log, not from the procedure manual. Find the common paths, the rework loops and the waits between steps.
About 25 minutes
The problem
Shieldline's procedure manual shows a neat claims process: register, check, inspect, approve, pay. In workshops, staff describe that process too. But the claims system has recorded every step of every claim, with a timestamp, in events.csv. That log shows how claims actually flow, including the loops and waits nobody draws on a whiteboard.
The concept
An event log
Each row is one step: a case (the claim), an activity, a timestamp and who did it (the team). Order the rows by case and time and you have each claim's path.
Variants
A variant is one distinct path through the process. The most common variant is the "happy path". How many claims follow it, and what the other variants have in common, tells you where the process breaks.
Rework
A loop back to an earlier step, here Documents requested → Documents received → Documents checked, repeated. Every loop adds days and work.
Waiting time versus working time
The gap between two steps is mostly waiting: the claim sits in a queue. Most of a slow process is waiting, not work. Find the longest gaps.
Example
The most common paths through the process, for baseline claims:
SQL
WITH paths AS (
SELECT claim_id, GROUP_CONCAT(activity, ' > ') AS path
FROM (SELECT * FROM events ORDER BY claim_id, timestamp)
GROUP BY claim_id
)
SELECT COUNT(*) AS claims,
ROUND(100.0 * COUNT(*) / (SELECT COUNT(*) FROM claims WHERE submitted_at < '2026-04-01'), 1) AS pct,
path
FROM paths JOIN claims USING (claim_id)
WHERE submitted_at < '2026-04-01'
GROUP BY path
ORDER BY claims DESC
LIMIT 5;claims pct path
1072 47.9 Claim submitted > Claim registered > Documents checked > Assessor assigned > Inspection > Assessment completed > Manager approval > Payment approved > Claim paid
562 25.1 Claim submitted > Claim registered > Documents checked > Documents requested > Documents received > Documents checked > Assessor assigned > Inspection > Assessment completed > Manager approval > Payment approved > Claim paid
120 5.4 Claim submitted > Claim registered > Documents checked > Documents requested > Documents received > Documents checked > Documents requested > Documents received > Documents checked > Assessor assigned > Inspection > Assessment completed > Manager approval > Payment approved > Claim paid
102 4.6 Claim submitted > Claim registered > Documents checked > Documents requested > Claim closed: no response
90 4 Claim submitted > Claim registered > Documents checked > Assessor assigned > Inspection > Assessment completed > Claim rejectedUnder half of claims follow the happy path. The next two variants are the same path with one or two document loops, and the fourth is a claim closed because the customer stopped responding after documents were requested. Documents are clearly a problem. Notice too that every claim, even a windscreen, goes through Inspection and Manager approval.
Now the waits. For each step, the time since the previous step, averaged over paid baseline claims:
SQL
WITH steps AS (
SELECT e.claim_id, e.activity,
LAG(e.activity) OVER (PARTITION BY e.claim_id ORDER BY e.timestamp) AS previous,
julianday(e.timestamp) - julianday(LAG(e.timestamp) OVER (PARTITION BY e.claim_id ORDER BY e.timestamp)) AS gap_days
FROM events e JOIN claims c USING (claim_id)
WHERE c.outcome = 'Paid' AND c.submitted_at < '2026-04-01'
)
SELECT previous || ' → ' || activity AS step,
COUNT(*) AS times,
ROUND(AVG(gap_days), 1) AS avg_days,
ROUND(SUM(gap_days) / (SELECT COUNT(*) FROM claims WHERE outcome = 'Paid' AND submitted_at < '2026-04-01'), 1) AS days_per_claim
FROM steps
WHERE previous IS NOT NULL
GROUP BY step
ORDER BY days_per_claim DESC;step times avg_days days_per_claim
Assessor assigned → Inspection 1904 6.3 6.3
Documents requested → Documents received 1018 5.9 3.1
Assessment completed → Manager approval 1904 3.1 3.1
Manager approval → Payment approved 1798 2.9 2.7
Inspection → Assessment completed 1904 2.2 2.2
Claim registered → Documents checked 1904 2 2
Payment approved → Claim paid 1904 1.7 1.7
Claim submitted → Claim registered 1904 1.3 1.3
Documents received → Documents checked 1018 2 1.1
Documents checked → Assessor assigned 1904 1 1
Manager approval → Head office approval 106 8.1 0.5
Head office approval → Payment approved 106 2.7 0.2
Documents checked → Documents requested 1018 0.2 0.1days_per_claim spreads each step's total wait over all paid claims, so the column adds up to the average days to settle. The longest single wait is between an assessor being assigned and the inspection: over six days. Then come waiting for the customer's documents, and waiting for the manager's approval.
Walkthrough
- Run both queries. Check that
days_per_claimadds up to about 25.2. - Draw the current process as a BPMN diagram with swimlanes for Customer or Agent, Claims desk, Assessors, Claims managers, Head office and Finance. Use the log, not the manual: include the document loop and the no-response exit.
- Mark each step with its average wait.
- Count how many document requests a claim can receive. What's the most?
- Describe the process in writing (the task below).
Practice
Practice
What percentage of baseline claims had documents requested at least once? One decimal place.
Practice
For paid baseline claims, what's the average wait in days between Assessor assigned and Inspection? One decimal place.
Task
8 minDescribe the current process as numbered steps (60 to 150 words): who does each step, the rework loop, and the three longest waits with their numbers.
Your work is checked for
- Numbered steps
- Names the teams (claims desk, assessor, manager, finance)
- Describes the document loop
- Mentions the inspection
- Gives waits in days
- Between 60 and 150 words